Host Engineering Forum

General Category => Do-more CPUs and Do-more Designer Software => Topic started by: Henryp on April 15, 2014, 01:00:24 PM

Title: 250 Out Do More In
Post by: Henryp on April 15, 2014, 01:00:24 PM
This PLC controls our raw water lake pumps. It is the first one we did. The count is now at four soon to be five.
Title: Re: 250 Out Do More In
Post by: franji1 on April 15, 2014, 01:13:30 PM
LOL! (at the picture)

By chance, did you try the DL to Do-more Migration Utility in Designer 1.3?  If so, what did it help on?  What did it NOT help with?  If you didn't use it, what went well in your own migration process, what were the stumbling blocks?
Title: Re: 250 Out Do More In
Post by: Henryp on April 15, 2014, 03:33:07 PM
I did it before the tool was available but I have used the tool on three other test programs and it worked very well.  Maybe I'll get a chance to use it  on the old DS5 code form my lake pumps and see how it works .